This document relates to 2020-12, the Eclipse Foundation's multi-project Simultaneous Release of December 2020.
Common information
- Simultaneous Release Requirements (aka must-dos)
- Simultaneous Release Plan - Information that stays the same for each release, like requirements for participation, communication channels, etc.
Release schedule
Release |
Date |
Span |
Due dates |
Notes |
|---|---|---|---|---|
2020-12 M1 |
Friday, October 16, 2020 |
10/09 to 10/16 |
|
3 weeks from 2020-09 GA |
2020-12 M2 |
Friday, November 6, 2020 |
10/30 to 11/06 |
3 weeks from M1 |
|
2020-12 M3 |
Friday, November 27, 2020 |
11/20 to 11/27 |
|
3 weeks from M2 |
2020-12 RC1 |
Friday, December 4, 2020 |
11/27 to 12/04 |
|
1 week from M3 |
2020-12 RC2 |
Friday, December 11, 2020 |
12/04 to 12/11 |
1 week from RC1 |
|
Quiet period |
12/11 to 12/15 |
No builds during "quiet period". It is assumed all code is done by the end of RC2. |
||
2020-12 GA |
Wednesday, December 16 2020 |
|
5 days from RC2 |