This document relates to 2025-06, the Eclipse Foundation's multi-project Simultaneous Release of June 2025.

Delayed M2

Note: Due to ongoing issues with the Eclipse Foundation infrastructure affecting or even preventing builds for projects contributing to SimRel (particularly including Eclipse Platform), we have delayed M2 by one week. The subsequent dates for M3 and RCs stay the same. We continuously monitor the status of Eclipse Foundation infrastructure and reevaluate further impact on the release schedule.

Common information

Release schedule

ReleaseDateSpanDue datesNotes
2025-06 M1Friday, April 11, 202504/04 to 04/11
  • Opt-in deadline (new projects only)
3 weeks from 2025-03 GA
2025-06 M2Friday, May 9 2, 202504/25 to 05/09 05/023 4 weeks from M1 (delayed by one week due to infrastructure issues)
2025-06 M3Friday, May 23, 202505/16 to 05/233 2 weeks from M2
2025-06 RC1Friday, May 30, 202505/23 to 05/30
  • No new features and APIs after this date!
  • New and Noteworthy entries due
1 week from M3
2025-06 RC2Friday, June 6, 202505/30 to 06/061 week from RC1
Quiet period06/06 to 06/10No builds. It is assumed all code is done by end of RC2.
2025-06 GAWednesday, June 11, 20255 days from RC2

Google Calendar Link

List of participating projects